The building work has stopped halfway through
Short answer
Make the site safe and identify what protection or temporary works are required. If statutory work has been abandoned or is not being prosecuted with due diligence, the continuing effect of the original notice and award should be reviewed; security for expenses may also be relevant if it was obtained.
Act: ss3(2), 6(8), 7, 10 and 12, as applicable
Government guidance: useful explanation, but not an authoritative interpretation of the law.
Industry practice: helpful where proportionate, but not a substitute for the Act or binding authority.
What the Act actually requires
The relevant statutory basis is ss3(2), 6(8), 7, 10 and 12, as applicable. Applied to this question, the important point is that the Party Wall etc. Act gives specific rights and procedures rather than a general power to regulate all neighbour building work. Make the site safe and identify what protection or temporary works are required. If statutory work has been abandoned or is not being prosecuted with due diligence, the continuing effect of the original notice and award should be reviewed; security for expenses may also be relevant if it was obtained.
What Government guidance says
Government guidance assumes that statutory works proceed in accordance with the notice, any agreement and any award. Material changes, abandonment, ownership changes or new disputes should therefore be checked against the statutory authority that originally permitted the work.
What is common practice?
Good practice is to compare the position on site with the notice, drawings, award and agreed variations as soon as something changes. The longer an unrecorded deviation continues, the harder it becomes to separate authorised work from a later dispute.
What should you do now?
Record the present site condition and compare the work now being carried out with the notice, drawings, award and any written variation. Raise any material difference promptly before further work makes the position harder to unwind.
What should you NOT do?
Do not assume the original paperwork automatically authorises a materially changed design, a new owner or indefinite delay. Re-check the statutory basis before the work continues.
Related Party Wall Problems
Understand the law → Party Wall Knowledge Base
Read the authority → Party Wall Case Law Library
Need professional help? → Coburns Party Wall
This page is provided by Coburns Party Wall for general information and educational purposes only. It is not legal advice and is not a substitute for advice on the facts of a particular matter. Party wall matters are fact-sensitive and the application of the Party Wall etc. Act 1996 may depend on the works, notices, ownership, appointments, drawings, agreements, awards and surrounding circumstances. Case summaries and practical guidance simplify potentially complex legal issues and should not be relied upon instead of the legislation, relevant judgments or appropriate professional or legal advice. If court proceedings, an injunction, an appeal or another legal remedy may be required, obtain appropriate legal advice promptly. Coburns Party Wall accepts no responsibility for loss arising from reliance on this resource without appropriate consideration of the particular circumstances.
